With two sprints left I’d focus on containment and a clear narrative for the demo. First I’d freeze noncritical changes, create a read-only canonical export of the Excel tracker and build a one-page dashboard (pivot + conditional formatting) that shows material status and pending handoffs for the demo. I’d assign field owners (5 people across PM, engineering, procurement) and run a 2-hour reconciliation to cut inconsistent entries by ~70% for the demo. For the post-demo roadmap I’d prioritize: 1) automated ingestion and validation (saves ~8 hours/week), 2) basic handoff workflow and notifications, 3) role-based views and audit trail. Backlog prioritization uses impact/cost (reduce manual effort, reduce meeting time by 50%) and delivers an MVP in 6–8 weeks, then iterative integrations with source systems in 3 months.